| No. | Uraian | SAT. | Koef. | Harga Satuan (Rp) |
Jumlah (Rp.) |
Referensi Harga |
|---|---|---|---|---|---|---|
| A | TENAGA KERJA | |||||
| Pekerja | OH | 1,0000 | 150.000 | 150.000 | Link | |
| Tukang Kayu | OH | 2,0000 | 250.000 | 500.000 | Link | |
| Kepala Tukang | OH | 0,2000 | 275.000 | 55.000 | Link | |
| Mandor | OH | 0,0500 | 300.000 | 15.000 | Link | |
| b. Jumlah Harga Pekerja | 720.000 | |||||
| B | BAHAN | |||||
| Dolken kayu Ø 8-10/400 cm | Batang | 1,7000 | 40.000 | 68.000 | Link | |
| Kayu | M3 | 0,2100 | 3.650.000 | 766.500 | Link | |
| Paku Biasa | Kg | 0,3000 | 40.000 | 12.000 | Link | |
| Semen Portland | Kg | 10,5000 | 3.650 | 38.325 | Link | |
| Pasir Beton | M3 | 0,0300 | 350.000 | 10.500 | Link | |
| Koral Beton | M3 | 0,0500 | 400.000 | 20.000 | Link | |
| Seng Gelombang | Buah | 1,5000 | 75.000 | 112.500 | Link | |
| a. Jumlah Harga Bahan | 1.027.825 | |||||
| C | ALAT KERJA | |||||
| Peralatan | Lot | 1,0000 | 10.000 | 10.000 | Link | |
| c. Jumlah Harga Alat | 10.000 | |||||
| d. Total (a+b+c) | 1.757.825 | |||||
| e. Keuntungan 10% | 175.783 | |||||
| Harga Satuan Pekerjaan (d+e) | 1.933.608 | |||||
| Pembulatan Harga Harsat | 1.933.600 | |||||