| No. | Uraian | SAT. | Koef. | Harga Satuan (Rp) |
Jumlah (Rp.) |
Referensi Harga |
|---|---|---|---|---|---|---|
| A | TENAGA KERJA | |||||
| Pekerja | OH | 0,0600 | 150.000 | 9.000 | Link | |
| Operator Alat | OH | 0,0600 | 250.000 | 15.000 | Link | |
| Kepala Tukang | OH | 0,0060 | 275.000 | 1.650 | Link | |
| Mandor | OH | 0,0060 | 300.000 | 1.800 | Link | |
| b. Jumlah Harga Pekerja | 27.450 | |||||
| B | BAHAN | |||||
| Pembersihan Area Kerja (Land Clearing) | M2 | 1,0000 | 0 | 0 | Link | |
| a. Jumlah Harga Bahan | 0 | |||||
| C | ALAT KERJA | |||||
| Peralatan | Lot | 1,0000 | 10.000 | 10.000 | Link | |
| c. Jumlah Harga Alat | 10.000 | |||||
| d. Total (a+b+c) | 37.450 | |||||
| e. Keuntungan 10% | 3.745 | |||||
| Harga Satuan Pekerjaan (d+e) | 41.195 | |||||
| Pembulatan Harga Harsat | 41.200 | |||||