| No. | Uraian | SAT. | Koef. | Harga Satuan (Rp) |
Jumlah (Rp.) |
Referensi Harga |
|---|---|---|---|---|---|---|
| A | TENAGA KERJA | |||||
| Pekerja | OH | 0,3000 | 150.000 | 45.000 | Link | |
| Tukang Batu | OH | 0,1000 | 250.000 | 25.000 | Link | |
| Kepala Tukang | OH | 0,0100 | 275.000 | 2.750 | Link | |
| Mandor | OH | 0,0150 | 300.000 | 4.500 | Link | |
| b. Jumlah Harga Pekerja | 77.250 | |||||
| B | BAHAN | |||||
| Batu Bata Merah (5x11x22) cm | Buah | 70,0000 | 1.500 | 105.000 | Link | |
| Semen Portland | Kg | 14,3700 | 2.200 | 31.614 | Link | |
| Pasir Pasang | M3 | 0,0400 | 350.000 | 14.000 | Link | |
| a. Jumlah Harga Bahan | 150.614 | |||||
| C | ALAT KERJA | |||||
| Peralatan | Lot | 1,0000 | 10.000 | 10.000 | Link | |
| c. Jumlah Harga Alat | 10.000 | |||||
| d. Total (a+b+c) | 237.864 | |||||
| e. Keuntungan 10% | 23.786 | |||||
| Harga Satuan Pekerjaan (d+e) | 261.650 | |||||
| Pembulatan Harga Harsat | 261.700 | |||||